• Elementary School #5 (Darden Hill Rd.)
    Budget: $37,500,000

    Scope of Work:

    Current Work:

    • Architects gathered stakeholder input at community meetings on August 27 and 28. The input received will assist architects in creating schematic designs for the site and the building.
    • A site feasibility study was created showing possible locations of the elementary school, while leaving open the potential to add other buidlings on the site. The feasibility study was presented to the Board on September 16, 2019.


    Update on Elementary #5 (9.4.19)

     

    Next Steps:

    • Construction is tentatively slated to start in the summer of 2020