• Elementary School #5 (Darden Hill Rd.)
    Budget: $37,500,000

    Scope of Work:

    Completed Work:

    • Architects gathered stakeholder input at community meetings on August 27 and 28. The input received will assist architects in creating schematic designs for the site and the building.
    • A site feasibility study was created showing possible locations of the elementary school, while leaving open the potential to add other buidlings on the site. The feasibility study was presented to the Board on September 16, 2019.
    • Design Input Committee met throughout the fall with the architects and representatives from the DSISD Facilities and Construction Department
    • Schematic Design process led into the Design Development phase


    Update on Elementary #5 (9.4.19)

    Schematic Design Presentation (12.16.19)


    Design Update (1.21.20)


    Current Work:

    • Ongoing communication with County on possible Darden Hill Road improvements

    Next Steps:

    • Development of construction documents
    • Bid process
    • Probable Guaranteed Maximum Price (GMP) recommendation to the Board of Trustees
    • Construction is tentatively slated to start in the summer of 2020