• High School Additions and Renovations
    Budget: $22,268,485

    Actual Expenditures: $21,961,477

     

    Scope of Work:

    • Expand student capacity to 2,500 with additional classrooms
    • Address approved assessment report upgrades
    • Courtyard building addition; including engineering, floral design, business/marketing, audio/visual, and physics spaces
    • Add new flexible gym
    • Expand ag barn

    Completed Work:

    • Underground utility work
    • Foundation work at both expansion wing and flexible gym space
    • Classroom at ag barn and pad for additional barn space
    • New ag barn building: foundation and utility work is ongoing
    • Structure, roofing, AC, lighting and stone veneer in flexible gym space
    • Structural steel for expansion wing, connecting new area to existing building
    • Mechanical, electrical and plumbing work at both expansion wing and flexible gym space
    • Structural steelwork of expansion wing
    • Roofing at both expansion wing and flexible gym space
    • Electrical and plumbing in ag barn
    • Dance expansion room structural work
    • Final work for Mechanical, electrical and plumbing in expansion wing
    • Glasswork, elevator, painting, floor polishing, exterior stone tile expansion wing
    • Installation of wash stations and pens in ag barn
    • Flooring and AV system in flex space
    • Interior of dance floor expansion
    • Interior work and technology hook-ups for both expansion wing
    • Renovation of existing building,
    • Conversation of existing labs into classrooms
    • Addition of a nurse's station